Wynnum Rugby Leagues Club Temporary Bridge

THE CHALLENGE

Wynnum Rugby Club is undergoing extension and refurbishment works. The extension works extended to use part of the car park for construction.  

To enable the rugby club to remain open to the general public a temporary bridge was needed to be constructed across a small creek. A temporary bridge that could support up to 60 tonne vehicle loads was crucial to the successful completion of the Rugby Clubs refurbishment works.

OUR SOLUTION

A new temporary bridge, the Mabey Compact 200 ™ (C200 ™) provided Daniels Civil with the perfect solution. 

A 12 metre, prefabricated bridge was assembled on site and installed ready for live traffic within two days by a team of four people and a Mabey supplied site supervisor. The bridge was 4.2 metres wide complete with Mabey SmartEdge supplied on the truss panels, configured to provide safe crossing for general public and construction vehicles up to 60 tonne.

THE RESULT

Mabey’s solution provided a temporary bridge that allowed for rapid deployment and operation, enabling Daniels Civil to respond to the dynamic conditions of the site and their client’s requirements.  

Mabey was able to provide an efficient and safe “off the shelf” solution to provide access to the rugby club. 