Planning a Temporary Bridge Hire Project 

A temporary bridge project starts with the crossing requirement, then develops through engineering, delivery and installation planning. The bridge system is one part of the solution. Ground conditions, approaches and the available site area also affect what can be delivered safely and efficiently. 

Mabey supports temporary bridge projects with equipment, engineering services, transport and preassembly. A complete project brief gives the team the information needed to discuss a practical arrangement before mobilisation. 

Quick Answer 

Begin with the required span, traffic type, ground information, site access and programme. Mabey’s engineering team can review the project brief, while its transport and preassembly service can support mobilisation planning. These elements should be considered together. 

Temporary Bridge Design Requirements 

Mabey’s Temporary Bridging page identifies the official product name as the Compact 200™ (C200™) system. It is a modular system for temporary and permanent applications. 

Imagine a crossing that must take site vehicles over a drainage line. The bridge is only one part of the task. The approaches must work, traffic needs a clear route and the ground must support the approved arrangement. 

Site Information Needed for Temporary Bridge Hire 

Gather drawings, survey data, approach levels, ground information, nearby services and details of the crossing. 

The delivery route is a practical priority. Trucks, lifting equipment and installation crews need enough room to reach the bridge location. Check the route from the site entrance through to the available laydown area. 

Mabey can review the project brief with the contractor before equipment is mobilised. 

Engineering Support for Temporary Bridge Projects 

Mabey Engineering Services provides temporary-works design support, structural plans and supporting calculations where required. 

Share the crossing details, expected loads and proposed work sequence with the engineering team. This allows the bridge, approaches and installation method to be considered as one project. 

Temporary Bridge Transport and Preassembly Planning 

Mabey Transport and Preassembly can support delivery and preparation for temporary bridge projects. 

Confirm the delivery route, unloading area, crane access, lifting plan and site induction requirements during the design phase. Preassembly may assist where the site has limited on-site labour or a restricted programme. 

Temporary Bridge Project Example 

Mabey’s Ropes Creek Temporary Vehicle Bridge provides a relevant project example for readers researching temporary bridge applications. 

Every crossing has its own conditions. The span, ground, delivery access and traffic requirements should be reviewed for the individual project rather than copied from another site. 

Temporary Bridge Hire Planning Checklist 

Information Required Why It Matters 
Required span and approach geometry Supports bridge layout and access planning 
Design loads and traffic type Informs the engineering brief 
Ground and survey information Affects supports and construction method 
Delivery route and lifting plan Shapes transport and installation planning 
Programme and approvals Helps align design, mobilisation and site readiness 

Talk to Mabey About Your Bridge Project 

Temporary bridge planning works best when engineering, access, transport and installation are addressed early. Mabey can review the project brief, support the engineering process and help plan delivery and preassembly. 

Talk with Mabey about this project 

Frequently Asked Questions 

Can a temporary bridge be used for pedestrians? 

Mabey describes footwalk options for the Compact 200™ system. The final design should address pedestrian use and access controls. 

Can a temporary bridge carry two lanes of traffic? 

Mabey’s current product information describes two-lane options for the C200™ system. Confirm the required configuration with Mabey’s engineering team. 

When should bridge engineering begin? 

Begin once the crossing requirement and site information are available. Early input gives more time to resolve design, access and approval matters. 

What should be provided before requesting a quote? 

Provide the crossing location, required span, design loads, site drawings, ground information, access details and programme requirements. 